Descripción de la contratación
The baseline scope of the TB12 Contract is design and build and includes design, construction, test and commissioning and taking-over by F4E of the following works:
1. PBS63/65 – B34 & B37 – neutral beam power supply buildings (B37 is Safety Relevant), including civil, M&E, finishing works, and surrounding area;
2. PBS 61/65: Area 30 – retention pits, foundations for transformers, segregation walls, embedded plates, base plates and associated M&E works;
3. PBS 61: Area 31 – foundations, embedded plates and base plates (All are Safety Relevant) for the SF6- IO equipment;
4. PBS 43/61 – LC09 Load Centre 09 and associated foundations;
5. PBS 43/61 – LC04 Load Centre 04 and associated foundations;
6. PBS 63/65 – B75 fast discharge and switching networks resistor building non-PIC/SR, design and build of the civil, M&E (services) and finishing works’ activities, and surrounding area;
7. PBS 62/65 - B71 Control Building (B71 North – Non-PIC and B71 South – PIC), construction and execution design only of civil, all fire topics, mechanical, electrical, HVAC, C&I, architectural finishing works and surrounding area but excluding execution design for B71 South PIC;
8. all infrastructures works (outside the buildings):
— all PBS61 (including SR components and PIC connection to Tokamak Complex) in TB12 construction areas. Note that PBS 61 baseline works do not include PBS 61 works around buildings not to be built under the scope of the baseline, e.g. B71 Baseline,
— all PBS 65 out of the buildings in TB12 construction areas. Note that these PBS 65 baseline works do not include PBS 65 works around buildings not to be built under the scope of the baseline, e.g. B71 Baseline,
— all PBS 26 in TB12 construction areas. Note that PBS 26 baseline works do not include PBS 26 works around buildings not to be built under the scope of the baseline, e.g. B71 Baseline,
— all PBS 43 in TB12 construction areas. Note that PBS 43 baseline works do not include PBS 43 works around buildings not to be built under the scope of the baseline, e.g. B71 Baseline;
9. project management – refer to Annex A (including detail list of PIC and SR components).
Note: The B75 fast discharge and switching networks resistor building is made of two buildings:
— B75 Non PIC/SR including CS & PF fast discharge resistors and switching network resistors,
— B75 PIC including TF fast discharge resistors.
The following options may be exercised in accordance with Sub-Clause 13.5 [Options] of the Conditions of Contract:
— Option 1: B71 North, Control Building, Non PIC, construction, test and commissioning and taking-over by F4E including the PBS61/26/65/43 infrastructure works around the B71 North,
— Option 2: cancelled (B71 South, Control Building PIC, execution design, construction, test and commissioning and taking-over by F4E including the PBS61/26/65/43 infrastructure works around the B71 South.),
— Option 3: B75 fast discharge and switching networks resistor building, PIC, design and build of the civil, M&E (services) and finishing works’ activities including design, construction, test & commissioning and Taking-Over by F4E. This option includes the surrounding PBS61/26/65/43 infrastructure works,
— Option 4: Cryoline Bridge from B52 to B74 and the Busbar Plant Bridges from B32 and B33 to B74, design and build of the civil, M&E (services) and finishing works’ activities including design, construction, test and commissioning and taking-over by F4E,
— Option 5: Supply and install PBS 44 cable trays for IO systems (excludes design),
— Option 6: cancelled two years operation and maintenance of the TB12 baseline scope and of exercised options after taking over,
— Option 7: cancelled Integrated commissioning with IO.
IO: Iter Organization
PIC: Protection Important Component.
SR: Safety Related.